HARTWOOD VILLAGE – AS OF FEBRUARY 2026
March 12, 2026
HARTWOOD VILLAGE
Percentage Completion:
Land Development: 14.61%
THE FOLLOWING ARE ONGOING WORKS FOR HARTWOOD VILLAGE:
– Ongoing Land development works
-
Drainage Works
-
Sewer line Works
-
Electrical UG Duct line
-
Auxiliary UG Duct line
-
Perimeter Fence Construction
– Clubhouse & Bathhouse
– Gateway 1 & 2 / Road & Street Lighting
Other lookahead works:
– Road / Street Lighting (Q3 2026)
– Clubhouse / Guardhouses & Gates Construction (Q4 2026)
– Swimming Pool, Deck, Pumphouse Construction (Q4 2026)
– Central Park Site Devt. (Q3 2026)
– Landscaping Works / Others (Q3 2026)
License to sell:
HLURB LS NO.: DHSUD Region 4A TLS 056 & 072
Project Location: Barangay Malamig, Biñan City, Laguna
Developer: Horizon Land Property Development Corp
Owner: Horizon Land Property Development Corp
Completion Date: June 2026 (Phase 1) January 2027 (Phase 2)