MARCO POLO PARKPLACE – AS OF December 31, 2025
January 28, 2026
MARCO POLO PARKPLACE
Percent completion: 28.06%
– Work on 11th floor, installation of reinforcing bars and columns and electrical and plumbing roughing-ins
– Ongoing installation of top floor (at time of photo – 10F)
– Ongoing installation of reinforcing bars of columns and beams
– Housekeeping properly maintained at floors ready to receive partitioning; safety nets/enclosures installed (low zone residential units)
– Ongoing installation of plumbing and sanitary lines; ongoing construction of reinforced partitions
– Ongoing construction of parapet walls and planters at the Upper Ground Floor
– Inspection with the general contractor and the supplier of aluminum windows, ensuring plumbness of window openings
– Ongoing installation of reinforcing bars of columns and beam
– Proper installation of secured scaffoldings and formworks to support ongoing or active floors above
– Housekeeping properly maintained at floors ready to receive partitioning; safety nets/enclosures/barriers installed (villa residential units)
– Storage of construction materials are sorted and maintaining proper housekeeping within the construction site
– Ongoing inspection by FLI Project Officer and the general contractor’s representative of installed reinforcing bars and roughing-ins
– Ongoing installation of electrical and plumbing roughing-ins
– Ongoing inspection by FLI Project Officer and the general contractor’s representative of installed reinforcing bars and roughing-ins
– Ongoing installation of electrical and plumbing roughing-ins; Ongoing concrete works of columns and beams
License to sell:
HLURB LS NO.: 0002142
Project Location: Nivel Hills, Brgy. Lahug, Cebu City
Developer: Federal Land, Inc.
Owner: Federal Land, Inc.
Completion Date: 31 July 2026