MARCO POLO PARKPLACE – AS OF November 30 2025
November 30, 2025
MARCO POLO PARKPLACE
Percentage of Completion: 25.46%
– Ongoing application of skim coat and primer paint on Basement 3.
– Ongoing surface preparation of walls through application of rubbed concrete on Basement 2.
– Ongoing application of skim coat and primer paint on Basement 2.
– Ongoing construction of CHB wall partitions on LGF.
– Ongoing construction of CHB walls and carpentry work on UGF.
– Ongoing installation of safety barriers and production of safety catchers on UGF.
License to sell:
HLURB LS NO.: 0002142
Project Location: Nivel Hills, Brgy. Lahug, Cebu City
Developer: Federal Land, Inc.
Owner: Federal Land, Inc.
Completion Date: 31 July 2026