Quantum Residences – AS OF MAY 2025
March 1, 2025

Quantum Residences
Amethyst Tower is 89.01% complete.
Construction Details:
– Ongoing Mechanical, Electrical, Plumbing, Fire, and Safety (MEPFS) and waterproofing works at Roof deck Level.
– Ongoing dry wall and ceiling works, painting works, and MEPFS works at the 25TH to 37TH Floor.
– Ongoing final painting and finishing works on the hallways of the 15TH and 18TH Floors.
– Substantial completion of building watertightness at the 6TH to 37TH Floor.
License to sell:
HLURB LS NO.: 034582
Project Location: Taft Avenue, Brgy. 49, Pasay City
Developer: Horizon Land Development Corp.
Owner: Horizon Land Development Corp.
Completion Date: Tower 1 (Aqua) | 31 December 2024
Tower 2 (Amethyst) | 31 December 2024
Tower 3 (Amber) | 31 December 2025