Siena Towers – AS OF MAY 2025
March 1, 2025

Siena Towers
Tower Two is 83% complete.
Construction Details:
– Ongoing landscaping works on the 5TH Floor
– Ongoing painting, ceiling, and framing works for the Amenity Lounge Room, Function Room, and Day Care Room on the 5TH Floor
– Completed residential units on the 6TH to 11TH Floor
– Ongoing finishing works on the 12TH to 15TH Floor
– Ongoing Mechanical, Electrical, Plumbing, Fire, and Safety (MEPFS) functionality test on the 16TH to 18TH Floor
– Ongoing painting works and installation of plumbing fixtures on the 17TH to 21ST Floor Ongoing installation of toilet and floor tiles on the 22ND Floor
License to sell:
HLURB LS NO.:
Project Location: Loyola Ave., cor Marquinton Drive, Brgy. Sto. Nino, Marikina City
Developer: Horizon Land Development Corp.
Owner: Horizon Land Development Corp.
Completion Date: December 31, 2025