Siena Towers – AS OF MAY 2025
Siena Towers
Tower Two is 83% complete.
Construction Details:
– Ongoing landscaping works on the 5TH Floor
– Ongoing painting, ceiling, and framing works for the Amenity Lounge Room, Function Room, and Day Care Room on the 5TH Floor
– Completed residential units on the 6TH to 11TH Floor
– Ongoing finishing works on the 12TH to 15TH Floor
– Ongoing Mechanical, Electrical, Plumbing, Fire, and Safety (MEPFS) functionality test on the 16TH to 18TH Floor
– Ongoing painting works and installation of plumbing fixtures on the 17TH to 21ST Floor Ongoing installation of toilet and floor tiles on the 22ND Floor
License to sell:
HLURB LS NO.:
Project Location: Loyola Ave., cor Marquinton Drive, Brgy. Sto. Nino, Marikina City
Developer: Horizon Land Development Corp.
Owner: Horizon Land Development Corp.
Completion Date: December 31, 2025
Digital Marketing Head
Martin is an experienced marketer with over 16 years of experience across various industries including real estate, banking and finance, technology, and advertising.
Martin has a broad range of expertise in having handled campaigns, brand launches, activations both in the traditional and digital space. Currently serving as the Digital Marketing Head at Federal Land, Martin leads a team focused on managing digital sales and platforms for the residential, estates and commercial business units.
linkedinExplore Our Latest News & Events
HARTWOOD VILLAGE – AS OF FEBRUARY 2026
THE GRAND MIDORI ORTIGAS – AS OF FEBRUARY 2026
MARCO POLO PARKPLACE – AS OF December 31, 2025