THE GRAND MIDORI ORTIGAS – AS OF JUNE 30, 2025
THE GRAND MIDORI ORTIGAS

Percentage of Completion:

Tower 1 – 99.73%
Tower 2 – 80.64%

 

THE FOLLOWING ARE ONGOING WORKS FOR THE GRAND MIDORI ORTIGAS:

– Ongoing Unit handover at 43rd floor level, Tower 1
– Ongoing BOH handover at 30th floor level, Tower 1
– Tile laying at hallway, 35th floor level, Tower 2
– Installation of kitchen counter top at level 12, Tower 2
– Enclosure of ceiling at Level 38, Tower 2
– Installed fountain signage.

 

License to sell:

HLURB LS NO.: 034640
Project Location: Exchange Road corner Jade Drive, Ortigas Center, Pasig City
Developer: Federal Land Inc.
Owner: Federal Land Inc.
Completion Date: Tower 1 – October 2024

Share:

Explore Our Latest News & Events

THE GRAND MIDORI ORTIGAS – AS OF APRIL 2026
April 23, 2026

THE GRAND MIDORI ORTIGAS – AS OF APRIL 2026

Read More
HARTWOOD VILLAGE – AS OF FEBRUARY 2026
March 12, 2026

HARTWOOD VILLAGE – AS OF FEBRUARY 2026

Read More
THE GRAND MIDORI ORTIGAS – AS OF FEBRUARY 2026
March 11, 2026

THE GRAND MIDORI ORTIGAS – AS OF FEBRUARY 2026

Read More
More news and Events

Cookie Policy

Federal Land, Inc. is committed in protecting your privacy. We promise to keep all the information you share confidential. To improve the customer experience, this website/page stores cookies but not personally identifiable information which are not shared to third-party entities. We assure you that the data you are providing us will be treated with utmost confidentiality. Learn More
i