MARCO POLO PARKPLACE – AS OF OCTOBER 2026
MARCO POLO PARKPLACE
Percent Completion: 52.32%
– Ongoing exterior wall repainting and installation of facade glass
– Ongoing installation of balcony railings
– Drywall partitioning is ongoing up to the 16th floor of the building
– Tiling works are ongoing up to the 9th floor (installation of living room, dining, kitchen, and balcony tiles)
– Balcony railings are ongoing at 9F, including waterproofing works
– Ongoing construction of drywall partitioning and tiling works
– Ongoing clearing of hallways in preparation for tiling works installation
– Ongoing exterior wall repainting and installation of facade glass
License to sell:
HLURB LS NO.: 0002142
Project Location: Nivel Hills, Brgy. Lahug, Cebu City
Developer: Federal Land, Inc.
Owner: Federal Land, Inc.
Completion Date: 31 July 2026