Percent Completion: 43.51%
– Ongoing stripping of forms of the building crown and parapet walls at the roof deck
– Ongoing plastering works on the machine room interior and exterior walls
– Ongoing installation of gondola supports in preparation for exterior walls surface preparation
– Ongoing setup of gondolas in preparation for exterior surface preparation
– Ongoing plastering works on exposed CHB walls
– Ongoing application of skim coat on walls and ceiling in preparation for primer paint application
– Ongoing wire tracing for both electrical and auxiliary rough-ins
– Ongoing floor layout of the internal dry wall partitions
License to sell:
HLURB LS NO.: 0002142
Project Location: Nivel Hills, Brgy. Lahug, Cebu City
Developer: Federal Land, Inc.
Owner: Federal Land, Inc.
Completion Date: 31 July 2026